Progress

25th May 2017
 
19% Complete

Whizdom Essence Sukhumvit

Construction Progress for May 25th, 2017.


Progress overview:

Progress % base on plan 14.61% of total project

Progress % base on actual 18.55% of total project

Actual progress is faster than plan 3.94% of total project (34 days)


This month's progress:

Infrastructure, swimming pool floor 6 - 25%

Infrastructure, concrete floor 7 - 100%

Infrastructure, concrete floor 8 - 50%

Infrastructure, concrete waste management area - 100%

Infrastructure, Lab room

Installation of TOWER CRANE


Next month planned progress:

Infrastructure, concrete floor 8 - 100%

Infrastructure, concrete floor 9 - 100%

Infrastructure, concrete floor 10 - 100%

Infrastructure, concrete floor 11 - 100%

Infrastructure, concrete, elevator + ladder till floor 12

Infrastructure, concrete waste management area - 100%

Architecture floor 6

Building system floor 6


In conclusion: Visavapat Co., Ltd., contractor, completed the construction up to floor 7.

Estimated to complete construction of infrastructure up to floor 11 and begin architecture for floor 6 unit within May 2017